402 pricing benchmarks to help you evaluate your construction quote.
Updated August 24, 2026 with 26 new quotes added in the last 30 days.
We analyzed 119 real construction quotes submitted to QuoteScore. The median fairness score was 60/100. On the quotes we flagged as overpriced, the median overcharge was $2,519.
| Line item from a real quote | Quoted | Fair range | Verdict |
|---|---|---|---|
| Mudroom Addition (Exterior Finished, Interior Unfinished) | $11,000 | $8,000–$20,000 | FAIR |
| Mudroom Addition (7x7, unfinished interior) | $11,000 | $7,000–$15,000 | FAIR |
| Install three helical piers for structural crack repair | $9,000 | — | FAIR |
Recent anonymized examples pulled live from our database. No names, companies, or addresses are ever shown.
| Service / Item | Low | Average | High |
|---|---|---|---|
| Allowances (% of total) (percent) | $0.5 | $2 | $5 |
| Artwork / Decor Allowance (GSF) | $0.25 | $1 | $4 |
| Design Contingency (% of total) (percent) | $3 | $8 | $15 |
| Escalation (annual %) (percent) | $3 | $5 | $8 |
| Furniture, Fixtures & Equipment (FF&E) (GSF) | $5 | $20 | $50 |
| GC Contingency (% of total) (percent) | $1 | $3 | $5 |
| Geogrid at Hardscape Areas (SF) | $2 | $5 | $10 |
| IT / Telecom Infrastructure Allowance (GSF) | $2 | $5 | $12 |
| Landscaping Allowance (GSF) | $0.5 | $2 | $6 |
| Over-excavation & Stone Backfill (CY) | $20 | $45 | $80 |
| Owner Contingency (% of total) (percent) | $3 | $7 | $12 |
| Phasing / Occupied Building Premium (percent) | $5 | $12 | $20 |
| Temporary Heating & Cooling Allowance (lump sum) | $25,000 | $75,000 | $200,000 |
| Temporary Roads / Site Access (lump sum) | $5,000 | $20,000 | $60,000 |
| Utility Connection / Tap Fees (lump sum) | $5,000 | $25,000 | $100,000 |
| Winterization / Cold Weather Concrete (CY) | $10 | $25 | $50 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| ACM (Aluminum Composite) Panels (SF) | $25 | $45 | $80 |
| Air Barrier / Vapor Barrier (SF) | $1 | $2.5 | $5 |
| Below-Grade Waterproofing (membrane) (SF) | $5 | $12 | $25 |
| Building Envelope (% of building) (percent) | $5 | $10 | $18 |
| Curtain Wall System (stick-built) (SF) | $40 | $75 | $130 |
| Curtain Wall System (unitized) (SF) | $60 | $100 | $175 |
| EIFS (Exterior Insulation Finish System) (SF) | $8 | $16 | $28 |
| Expansion Joint Cover (LF) | $40 | $90 | $175 |
| Fiber Cement Panel / Siding (SF) | $8 | $16 | $28 |
| Fluid-Applied Air/Vapor Barrier (SF) | $2 | $5 | $10 |
| Green / Vegetative Roof (SF) | $15 | $30 | $60 |
| Insulation - Rigid Board (SF) | $1.5 | $3 | $6 |
| Insulation - Spray Foam (SF) | $2 | $4 | $8 |
| Metal Wall Panels (SF) | $15 | $30 | $55 |
| Precast Concrete Wall Panel (SF) | $25 | $50 | $85 |
| Rainscreen Panel System (SF) | $25 | $50 | $90 |
| Roof Hatch (each) | $1,500 | $3,000 | $6,000 |
| Roof Insulation (tapered cricket system) (SF) | $3 | $6 | $12 |
| Roofing ($/GSF) (GSF) | $4 | $10 | $22 |
| Roofing - Built-Up / Modified Bitumen (SQ) | $500 | $900 | $1,500 |
| Roofing - Standing Seam Metal (SQ) | $800 | $1,400 | $2,400 |
| Roofing - TPO/PVC Membrane (SQ) | $600 | $1,100 | $1,800 |
| Sheet Metal Flashing / Trim (LF) | $8 | $20 | $40 |
| Skylight (SF) | $60 | $110 | $200 |
| Spray Fireproofing (SF) | $1.5 | $2.75 | $5 |
| Waterproofing, Caulking & Sealants (GSF) | $1 | $3 | $7 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Concrete (% of building cost) (percent) | $3 | $6 | $12 |
| Concrete (overall $/GSF) (GSF) | $10 | $22 | $45 |
| Concrete Columns (CY) | $600 | $1,100 | $1,800 |
| Concrete Curb (interior) (LF) | $15 | $30 | $55 |
| Concrete Pumping (CY) | $15 | $30 | $55 |
| Concrete Saw Cutting (LF) | $3 | $6 | $12 |
| Concrete Sealer / Hardener (SF) | $0.5 | $1.25 | $2.5 |
| Concrete Stair (cast-in-place) (flight) | $3,000 | $7,000 | $15,000 |
| Concrete Topping/Overlay (SF) | $3 | $6 | $11 |
| Concrete Walls (structural) (SF) | $15 | $30 | $55 |
| Elevated Concrete Slab (cast-in-place) (SF) | $12 | $22 | $38 |
| Elevated Concrete Slab (post-tension) (SF) | $10 | $18 | $30 |
| Fiber Reinforcement (CY) | $8 | $15 | $30 |
| Foundation Walls (CY) | $400 | $700 | $1,200 |
| Grout / Non-Shrink Grout (CF) | $15 | $35 | $65 |
| Precast Concrete Panels (SF) | $20 | $40 | $70 |
| Precast Concrete Stair (flight) | $5,000 | $12,000 | $25,000 |
| Rebar (#4 installed) (ton) | $1,200 | $1,800 | $2,800 |
| Slab on Grade (4" standard) (SF) | $4 | $7 | $12 |
| Slab on Grade (6" reinforced) (SF) | $6 | $10 | $16 |
| Spread Footings (CY) | $350 | $600 | $1,000 |
| Tilt-Up Wall Panels (SF) | $12 | $22 | $38 |
| Vapor Barrier (under slab) (SF) | $0.3 | $0.75 | $1.5 |
| Wire Mesh (welded) (SF) | $0.5 | $1 | $2 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Conduit (EMT, average) (LF) | $8 | $18 | $35 |
| EV Charging Station (Level 2) (each) | $3,000 | $7,000 | $15,000 |
| Electrical (% of building) (percent) | $8 | $14 | $22 |
| Electrical System ($/GSF, healthcare) (GSF) | $35 | $60 | $100 |
| Electrical System ($/GSF, office) (GSF) | $18 | $32 | $55 |
| Electrical System ($/GSF, warehouse) (GSF) | $6 | $14 | $28 |
| Electrical incl. Fire Alarm (healthcare) (GSF) | $40 | $65 | $110 |
| Emergency Generator (kW) | $300 | $600 | $1,200 |
| Final Electrical Usage (allowance) (month) | $2,000 | $8,000 | $20,000 |
| LED Lighting (architectural) (SF) | $6 | $12 | $25 |
| LED Lighting (standard) (SF) | $3 | $6 | $12 |
| Lightning Protection System (GSF) | $0.5 | $1.5 | $3.5 |
| Low Voltage / Data Cabling (GSF) | $2 | $5 | $12 |
| Motor Control Center (each) | $15,000 | $40,000 | $100,000 |
| Panelboard (each) | $2,000 | $5,000 | $12,000 |
| Photovoltaic Solar Array (watt) | $2 | $3 | $5 |
| Power Distribution (branch wiring) (GSF) | $5 | $10 | $20 |
| Security / Access Control (GSF) | $1 | $3 | $8 |
| Switchgear / Main Distribution (each) | $25,000 | $75,000 | $200,000 |
| Transfer Switch (automatic) (each) | $5,000 | $15,000 | $35,000 |
| Transformer (dry type) (kVA) | $30 | $60 | $120 |
| UPS (Uninterruptible Power Supply) (kVA) | $200 | $500 | $1,000 |
| Wire / Cable (average per circuit) (each) | $200 | $500 | $1,200 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Access Flooring (raised floor) (SF) | $10 | $20 | $40 |
| Acoustic Wall Panel (SF) | $10 | $22 | $45 |
| Acoustical Ceiling Tile (2x2 grid) (SF) | $4 | $7 | $12 |
| Acoustical Ceiling Tile (2x4 grid) (SF) | $3 | $5.5 | $10 |
| Ceiling (drywall, painted) (SF) | $4 | $8 | $14 |
| Ceiling (specialty / clouds / soffits) (SF) | $12 | $25 | $50 |
| Ceramic Wall Tile (standard) (SF) | $8 | $15 | $28 |
| Countertop (laminate) (LF) | $25 | $50 | $100 |
| Countertop (quartz/granite) (LF) | $65 | $130 | $250 |
| Countertop (solid surface) (LF) | $50 | $100 | $200 |
| Drywall (1 layer, taped & finished) (SF) | $2 | $3.5 | $6 |
| Drywall (2-layer fire-rated) (SF) | $3.5 | $6 | $10 |
| FRP / Wall Panels (SF) | $4 | $8 | $15 |
| Hard Flooring - Ceramic Tile (SF) | $6 | $12 | $22 |
| Hard Flooring - LVT/LVP (commercial) (SF) | $4 | $7 | $13 |
| Hard Flooring - Porcelain Tile (SF) | $8 | $15 | $28 |
| Metal Stud Framing (SF wall) | $3 | $6 | $11 |
| Metal Studs & Drywall ($/GSF) (GSF) | $8 | $18 | $38 |
| Painting ($/GSF of building) (GSF) | $2 | $4 | $9 |
| Painting (interior, commercial) (SF wall) | $1 | $2.5 | $5 |
| Polished Concrete (SF) | $3 | $7 | $14 |
| Resilient Sheet Flooring (SF) | $3 | $6 | $10 |
| Resinous / Epoxy Flooring (SF) | $5 | $12 | $25 |
| Rubber Flooring (gym/sports) (SF) | $6 | $12 | $22 |
| Shower / Tub Surround (solid surface) (each) | $1,500 | $3,500 | $7,000 |
| Soft Flooring - Broadloom Carpet (SF) | $2.5 | $5 | $9 |
| Soft Flooring - Carpet Tile (commercial) (SF) | $3 | $6 | $11 |
| Stained / Sealed Concrete (SF) | $3 | $6 | $12 |
| Stone Wall Cladding (interior) (SF) | $20 | $45 | $85 |
| Terrazzo Flooring (SF) | $15 | $30 | $55 |
| Toilet Accessories (each room) | $200 | $500 | $1,000 |
| Toilet Partitions (each) | $500 | $1,000 | $2,000 |
| Wall Base (rubber/vinyl) (LF) | $2 | $4 | $8 |
| Wall Protection (corner guards, handrails) (LF) | $15 | $35 | $70 |
| Wallcovering (vinyl, Type II) (SF) | $2 | $4 | $8 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Fire Alarm (% of building) (percent) | $1 | $2 | $3.5 |
| Fire Alarm System (GSF) | $2 | $4.5 | $9 |
| Fire Pump (each) | $25,000 | $50,000 | $90,000 |
| Fire Sprinkler (% of building) (percent) | $1 | $2 | $3.5 |
| Fire Sprinkler - Light Hazard (head) | $120 | $200 | $350 |
| Fire Sprinkler - Ordinary Hazard (head) | $150 | $250 | $400 |
| Fire Sprinkler System ($/GSF) (GSF) | $2.5 | $5.5 | $10 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Admin / Document Control (monthly) (month) | $4,000 | $6,500 | $10,000 |
| As-Built Drawings (lump sum) | $3,000 | $10,000 | $25,000 |
| Assistant Superintendent (monthly) (month) | $7,000 | $11,000 | $16,000 |
| BIM / Virtual Construction (lump sum) | $10,000 | $40,000 | $100,000 |
| Commissioning (Cx) Agent (GSF) | $0.5 | $1.5 | $3.5 |
| Dumpster & Waste Removal (monthly) (month) | $1,000 | $2,500 | $5,000 |
| Field Office Trailer (monthly) (month) | $800 | $1,500 | $2,500 |
| Final Cleaning (GSF) | $0.15 | $0.35 | $0.6 |
| General Conditions (% of total) (percent) | $4 | $6.5 | $9 |
| LEED / Green Building Certification (lump sum) | $15,000 | $50,000 | $150,000 |
| Material Hoist (monthly) (month) | $3,000 | $7,000 | $15,000 |
| Mobile Crane (daily) (day) | $1,500 | $3,500 | $7,000 |
| Preconstruction Services (lump sum) | $15,000 | $35,000 | $75,000 |
| Project Engineer (monthly) (month) | $7,500 | $10,000 | $14,000 |
| Project Manager (monthly) (month) | $12,000 | $16,000 | $22,000 |
| QA/QC Manager (monthly) (month) | $8,000 | $12,000 | $17,000 |
| Safety Manager (monthly) (month) | $6,000 | $9,000 | $13,000 |
| Scaffolding (monthly per SF face) (SF) | $1 | $3 | $6 |
| Superintendent (monthly) (month) | $10,000 | $14,000 | $19,000 |
| Survey / Layout (lump sum) | $5,000 | $15,000 | $40,000 |
| Temporary Fencing (linear foot) (LF) | $5 | $12 | $22 |
| Temporary Power & Utilities (monthly) (month) | $500 | $1,500 | $3,000 |
| Temporary Toilets (monthly) (month) | $200 | $400 | $700 |
| Testing & Inspections (3rd party) (lump sum) | $10,000 | $35,000 | $100,000 |
| Tower Crane (monthly rental) (month) | $15,000 | $35,000 | $65,000 |
| Winter Protection / Enclosures (monthly) (month) | $5,000 | $20,000 | $50,000 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| AHU (Air Handling Unit) (CFM) | $4 | $8 | $15 |
| Boiler (commercial) (each) | $15,000 | $40,000 | $80,000 |
| Chiller (air-cooled) (ton) | $1,200 | $2,200 | $4,000 |
| Chiller (water-cooled) (ton) | $800 | $1,600 | $3,000 |
| Controls / BAS (Building Automation) (GSF) | $2 | $5 | $12 |
| Cooling Tower (ton) | $400 | $800 | $1,500 |
| Ductwork (lb) | $5 | $9 | $16 |
| Ductwork Insulation (SF) | $2 | $4 | $8 |
| Fume Hood (laboratory) (each) | $5,000 | $12,000 | $25,000 |
| Geothermal Loop Field (ton) | $3,000 | $5,500 | $9,000 |
| HVAC (% of building) (percent) | $10 | $16 | $25 |
| HVAC System ($/GSF, healthcare) (GSF) | $40 | $65 | $100 |
| HVAC System ($/GSF, office) (GSF) | $20 | $35 | $60 |
| HVAC System ($/GSF, warehouse) (GSF) | $5 | $12 | $25 |
| Heat Recovery Unit / ERV (CFM) | $3 | $7 | $14 |
| Humidification System (each) | $5,000 | $15,000 | $35,000 |
| Kitchen Exhaust Hood & Makeup Air (each) | $8,000 | $20,000 | $45,000 |
| RTU (Rooftop Unit, per ton) (ton) | $1,500 | $3,000 | $5,500 |
| Refrigerant Piping (LF) | $20 | $50 | $100 |
| Temporary Heating & Cooling (allowance) (month) | $5,000 | $15,000 | $30,000 |
| Test & Balance (GSF) | $0.3 | $0.75 | $1.5 |
| VAV Box (each) | $1,500 | $3,000 | $5,500 |
| VRF System (Variable Refrigerant Flow) (ton) | $2,000 | $3,500 | $6,000 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Architects & Engineers Fee (percent) | $5 | $8 | $14 |
| Associated Costs / Soft Costs (% of total) (percent) | $4 | $7 | $12 |
| Builders Risk Insurance (% of total) (percent) | $0.3 | $0.75 | $1.5 |
| Building Permit Fees (% of total) (percent) | $0.2 | $0.5 | $1.5 |
| Construction Fee / GC Profit (% of total) (percent) | $2 | $4 | $7 |
| Construction Management Fee (percent) | $3 | $5 | $8 |
| Environmental Impact Study (lump sum) | $5,000 | $25,000 | $75,000 |
| General Liability Insurance (% of total) (percent) | $0.8 | $1.25 | $2 |
| Geotechnical Investigation (lump sum) | $3,000 | $15,000 | $50,000 |
| Impact / Development Fees (lump sum) | $5,000 | $50,000 | $250,000 |
| OCIP / CCIP (Wrap-Up Insurance) (percent) | $1.5 | $3 | $5 |
| Owner/Design Contingency (% of total) (percent) | $3 | $7 | $12 |
| Performance & Payment Bond (% of total) (percent) | $0.5 | $1 | $2 |
| Plan Review Fees (lump sum) | $5,000 | $25,000 | $75,000 |
| Project Management Software (percent) | $0.1 | $0.35 | $0.75 |
| Subdefault Insurance (% of total) (percent) | $0.5 | $1.25 | $2.5 |
| Utility Relocation (lump sum) | $10,000 | $50,000 | $200,000 |
| Workers Comp (blended rate) (percent) | $3 | $8 | $15 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Concrete Finisher (hour) | $40 | $65 | $100 |
| Drywall Finisher (hour) | $35 | $55 | $85 |
| Electrician (journeyman) (hour) | $55 | $85 | $130 |
| General Labor (burdened) (hour) | $35 | $55 | $85 |
| Glazier (hour) | $45 | $75 | $120 |
| HVAC / Sheet Metal Worker (hour) | $50 | $80 | $125 |
| Insulator (mechanical) (hour) | $45 | $70 | $110 |
| Ironworker (hour) | $55 | $90 | $140 |
| Laborer (demolition) (hour) | $30 | $45 | $70 |
| Operating Engineer (crane) (hour) | $60 | $95 | $150 |
| Painter (commercial) (hour) | $35 | $55 | $85 |
| Plumber (journeyman) (hour) | $55 | $85 | $130 |
| Roofer (hour) | $35 | $55 | $90 |
| Skilled Carpenter (hour) | $45 | $70 | $110 |
| Sprinkler Fitter (hour) | $55 | $85 | $130 |
| Tile Setter (hour) | $40 | $65 | $100 |
| Welder (certified) (hour) | $55 | $85 | $135 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Total MEP ($/GSF, data center) (GSF) | $100 | $200 | $400 |
| Total MEP ($/GSF, education) (GSF) | $60 | $100 | $165 |
| Total MEP ($/GSF, healthcare) (GSF) | $100 | $170 | $280 |
| Total MEP ($/GSF, hotel) (GSF) | $45 | $80 | $140 |
| Total MEP ($/GSF, laboratory) (GSF) | $150 | $250 | $400 |
| Total MEP ($/GSF, multifamily) (GSF) | $35 | $65 | $110 |
| Total MEP ($/GSF, office) (GSF) | $55 | $85 | $135 |
| Total MEP ($/GSF, retail) (GSF) | $25 | $45 | $80 |
| Total MEP ($/GSF, warehouse) (GSF) | $12 | $25 | $50 |
| Total MEP (% of building cost) (percent) | $25 | $35 | $45 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Brick Veneer (SF) | $12 | $22 | $38 |
| CMU Wall (12" reinforced/grouted) (SF) | $15 | $25 | $42 |
| CMU Wall (8" standard) (SF) | $10 | $18 | $30 |
| Masonry ($/GSF of building) (GSF) | $1 | $4 | $10 |
| Stone Veneer (SF) | $20 | $40 | $70 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Automatic Sliding Door (entrance) (each) | $5,000 | $10,000 | $18,000 |
| Doors, Frames & Hardware ($/GSF) (GSF) | $4 | $10 | $22 |
| Glass & Glazing ($/GSF) (GSF) | $2 | $6 | $15 |
| Hollow Metal Door & Frame (each) | $600 | $1,200 | $2,200 |
| Overhead/Coiling Door (each) | $2,000 | $5,000 | $12,000 |
| Sliding Patient/Barn Door (each) | $1,500 | $3,500 | $6,000 |
| Storefront / Curtain Wall (SF) | $35 | $70 | $125 |
| Window (commercial aluminum) (SF) | $25 | $50 | $90 |
| Wood Door & Frame (each) | $400 | $800 | $1,500 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| ADA Shower (complete) (each) | $2,000 | $5,000 | $10,000 |
| Backflow Preventer (each) | $1,500 | $4,000 | $9,000 |
| Domestic Water Piping (LF) | $15 | $35 | $70 |
| Drinking Fountain / Bottle Filler (each) | $1,500 | $3,500 | $6,000 |
| Floor Drain (each) | $300 | $700 | $1,500 |
| Grease Interceptor (interior) (each) | $2,000 | $5,000 | $12,000 |
| Hydronic Piping (heating) (LF) | $25 | $55 | $100 |
| Lavatory / Sink (each) | $500 | $1,200 | $2,500 |
| Medical Gas System (outlet) | $1,500 | $3,500 | $6,000 |
| Natural Gas Piping (LF) | $15 | $35 | $70 |
| Plumbing (% of building) (percent) | $4 | $8 | $15 |
| Plumbing System ($/GSF) (GSF) | $8 | $18 | $40 |
| Plumbing incl. Hydronic Piping (healthcare) (GSF) | $20 | $45 | $80 |
| Roof Drain (each) | $500 | $1,200 | $2,500 |
| Sanitary/Waste Piping (LF) | $20 | $45 | $85 |
| Water Closet (toilet) (each) | $400 | $900 | $1,800 |
| Water Heater (commercial) (each) | $3,000 | $8,000 | $20,000 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| ADA Compliance Upgrades (GSF) | $5 | $15 | $35 |
| Adaptive Reuse (warehouse to office) (GSF) | $80 | $160 | $300 |
| Adaptive Reuse (warehouse to residential) (GSF) | $100 | $200 | $375 |
| Asbestos Abatement (SF) | $3 | $10 | $25 |
| Elevator Modernization (each) | $75,000 | $150,000 | $300,000 |
| Healthcare Renovation (GSF) | $150 | $300 | $500 |
| Historic Renovation / Restoration (GSF) | $200 | $400 | $700 |
| Interior Demolition (selective) (GSF) | $2 | $6 | $15 |
| Lead Paint Abatement (SF) | $5 | $12 | $28 |
| Mold Remediation (SF) | $10 | $25 | $60 |
| Restaurant Buildout (GSF) | $100 | $200 | $400 |
| Retail Buildout (GSF) | $40 | $85 | $175 |
| Roof Replacement (commercial) (SQ) | $500 | $1,000 | $1,800 |
| Seismic Retrofit (GSF) | $15 | $40 | $80 |
| Tenant Improvement - Basic (office) (GSF) | $30 | $60 | $100 |
| Tenant Improvement - High-End (office) (GSF) | $100 | $175 | $300 |
| Tenant Improvement - Mid-Range (office) (GSF) | $60 | $110 | $175 |
| Window Replacement (commercial) (each) | $800 | $2,000 | $4,500 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Aggregate Base Course (CY) | $25 | $45 | $75 |
| Asphalt Paving (heavy duty) (SY) | $14 | $22 | $40 |
| Asphalt Paving (standard lot) (SY) | $8 | $14 | $25 |
| Bollards (steel, concrete filled) (each) | $500 | $1,200 | $2,500 |
| Concrete Curb & Gutter (LF) | $15 | $30 | $55 |
| Concrete Paving / Sidewalks (SF) | $5 | $10 | $18 |
| Deep Foundations / Piles (each) | $2,000 | $5,000 | $12,000 |
| Demolition (building) (GSF) | $3 | $8 | $18 |
| Detention / Retention Pond (each) | $25,000 | $75,000 | $200,000 |
| Dewatering (monthly) (month) | $3,000 | $10,000 | $30,000 |
| Earthwork & Erosion Control (acre) | $50,000 | $150,000 | $300,000 |
| Erosion Control / SWPPP (acre) | $3,000 | $8,000 | $20,000 |
| Fencing - Chain Link (6ft) (LF) | $15 | $30 | $50 |
| Fencing - Ornamental Steel (LF) | $35 | $70 | $120 |
| Fill & Compaction (CY) | $8 | $18 | $35 |
| Geotextile Fabric (SY) | $1 | $3 | $6 |
| Grease Trap / Interceptor (each) | $3,000 | $8,000 | $20,000 |
| Landscape & Irrigation (GSF) | $1.5 | $4 | $10 |
| Mass Excavation (CY) | $5 | $12 | $25 |
| Retaining Wall (concrete) (SF face) | $25 | $55 | $100 |
| Rock Excavation (CY) | $25 | $60 | $120 |
| Sanitary Sewer (per LF pipe) (LF) | $55 | $145 | $300 |
| Site Concrete (curbs, aprons) (SF) | $8 | $16 | $28 |
| Site Lighting / Poles (each) | $3,000 | $6,000 | $12,000 |
| Sitework (% of total) (percent) | $3 | $7 | $15 |
| Soil Remediation / Environmental (CY) | $50 | $150 | $400 |
| Soil Stabilization / Lime Treatment (SY) | $3 | $8 | $16 |
| Storm Utilities (per LF pipe) (LF) | $60 | $150 | $300 |
| Striping / Pavement Markings (LF) | $0.5 | $1.5 | $3 |
| Tree Removal / Clearing (per acre) (acre) | $2,000 | $6,000 | $15,000 |
| Underground Detention System (CY storage) | $40 | $80 | $150 |
| Water Utilities (per LF pipe) (LF) | $50 | $130 | $275 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Commercial Kitchen Equipment (GSF) | $15 | $40 | $80 |
| Conveying / Material Handling (GSF) | $0.5 | $3 | $8 |
| Corner Guards (stainless) (each) | $40 | $80 | $150 |
| Elevator - Hydraulic (2 stop) (each) | $60,000 | $90,000 | $140,000 |
| Elevator - Traction (multi-stop) (each) | $120,000 | $200,000 | $350,000 |
| Exterior Signage (illuminated) (each) | $5,000 | $20,000 | $60,000 |
| Fire Extinguisher Cabinet (each) | $200 | $400 | $800 |
| Flag Pole (each) | $2,000 | $5,000 | $12,000 |
| Furnishings (Window Treatments) (SF window) | $8 | $18 | $40 |
| Furnishings (general) (GSF) | $0.5 | $2 | $6 |
| Interior Signage / Wayfinding (GSF) | $0.5 | $2 | $5 |
| Laundry Equipment (commercial) (each) | $5,000 | $15,000 | $35,000 |
| Loading Dock Equipment (leveler + shelter) (each) | $8,000 | $18,000 | $35,000 |
| Medical Equipment (OFCI allowance) (GSF) | $5 | $20 | $60 |
| Operable Partition / Folding Wall (SF) | $40 | $80 | $150 |
| Projection Screen / AV System (per room) (each) | $5,000 | $15,000 | $40,000 |
| Specialties (signage, accessories, misc) (GSF) | $1 | $3.5 | $8 |
| Trash / Linen Chute (floor) | $5,000 | $10,000 | $20,000 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Embed Plates (each) | $50 | $150 | $350 |
| Light Gauge Steel Framing (SF wall) | $5 | $9 | $16 |
| Metal Decking (SF) | $3 | $5.5 | $9 |
| Miscellaneous Metals (stairs, rails, embeds) (GSF) | $1 | $3 | $7 |
| Shear Stud Connectors (each) | $2 | $5 | $10 |
| Steel Handrail / Guardrail (LF) | $50 | $120 | $250 |
| Steel Joists (ton) | $2,500 | $4,000 | $6,500 |
| Steel Lintels (LF) | $15 | $35 | $70 |
| Steel Stair (fabricated & installed) (flight) | $5,000 | $12,000 | $25,000 |
| Structural Steel ($/GSF) (GSF) | $8 | $18 | $40 |
| Structural Steel (% of building) (percent) | $4 | $8 | $15 |
| Structural Steel (fabricated & erected) (ton) | $3,500 | $5,500 | $8,500 |
| Structural Steel Connections (moment frame) (each) | $500 | $1,500 | $3,500 |
| Structural Steel Painting / Coating (SF) | $2 | $5 | $10 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| AV System (conference room) (each) | $5,000 | $20,000 | $50,000 |
| Access Control (per door) (each) | $1,500 | $3,000 | $6,000 |
| CCTV / Surveillance (per camera) (each) | $1,500 | $3,500 | $7,000 |
| DAS (Distributed Antenna System) (GSF) | $1 | $3 | $7 |
| Nurse Call System (healthcare) (bed) | $2,000 | $5,000 | $10,000 |
| Paging / Intercom System (GSF) | $0.5 | $1.5 | $3.5 |
| Structured Cabling (per drop) (each) | $150 | $300 | $550 |
| Technology Systems ($/GSF total) (GSF) | $3 | $8 | $20 |
| Wireless Access Point (installed) (each) | $500 | $1,200 | $2,500 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Car Wash (express/tunnel) (GSF) | $200 | $350 | $550 |
| Church / Worship (GSF) | $150 | $250 | $400 |
| Convention Center (GSF) | $250 | $400 | $600 |
| Correctional / Detention Facility (GSF) | $275 | $425 | $650 |
| Courthouse / Government (GSF) | $300 | $450 | $650 |
| Data Center (Shell & Core) (GSF) | $250 | $400 | $650 |
| Dental Office (GSF) | $200 | $325 | $500 |
| Dialysis Center (GSF) | $275 | $425 | $625 |
| Distribution Center (GSF) | $65 | $110 | $175 |
| Fire Station (GSF) | $300 | $450 | $650 |
| Fitness / Recreation Center (GSF) | $175 | $275 | $425 |
| Gas Station / Convenience Store (GSF) | $175 | $300 | $475 |
| Higher Education / University (GSF) | $275 | $425 | $600 |
| Hospital (per bed) (each) | $1,200,000 | $2,000,000 | $3,200,000 |
| Hospital / Acute Care (GSF) | $400 | $575 | $800 |
| Hotel (Full Service/Luxury) (GSF) | $300 | $475 | $700 |
| Hotel (Select Service) (GSF) | $175 | $275 | $400 |
| Hotel (per key, full service) (each) | $175,000 | $300,000 | $500,000 |
| Hotel (per key, select service) (each) | $80,000 | $130,000 | $200,000 |
| Industrial / Warehouse (GSF) | $75 | $135 | $225 |
| K-12 School (GSF) | $200 | $325 | $475 |
| K-12 School (per student) (each) | $30,000 | $50,000 | $80,000 |
| Laboratory / R&D Facility (GSF) | $350 | $550 | $800 |
| Library (GSF) | $275 | $425 | $600 |
| Medical Office Building (GSF) | $250 | $375 | $550 |
| Mixed-Use (retail + residential) (GSF) | $175 | $300 | $475 |
| Multifamily (per unit, garden style) (each) | $120,000 | $185,000 | $275,000 |
| Multifamily (per unit, high-rise) (each) | $275,000 | $425,000 | $650,000 |
| Multifamily (per unit, mid-rise) (each) | $175,000 | $280,000 | $425,000 |
| Multifamily Residential (Concrete/Steel) (GSF) | $225 | $350 | $500 |
| Multifamily Residential (Wood Frame) (GSF) | $150 | $225 | $350 |
| Office Building (Class A) (GSF) | $200 | $300 | $450 |
| Office Building (Class B) (GSF) | $150 | $225 | $325 |
| Outpatient / Ambulatory Surgery Center (GSF) | $300 | $450 | $650 |
| Parking Garage (Above Grade) (GSF) | $50 | $80 | $125 |
| Parking Garage (Below Grade) (GSF) | $80 | $130 | $200 |
| Performing Arts / Theater (GSF) | $350 | $550 | $850 |
| Pre-Engineered Metal Building (GSF) | $25 | $50 | $90 |
| Rehabilitation / Behavioral Health Facility (GSF) | $350 | $500 | $700 |
| Restaurant (GSF) | $250 | $400 | $600 |
| Retail / Shopping Center (GSF) | $100 | $185 | $300 |
| Self-Storage Facility (GSF) | $35 | $60 | $100 |
| Senior Living (per unit) (each) | $150,000 | $250,000 | $400,000 |
| Senior Living / Assisted Living (GSF) | $200 | $325 | $475 |
| Single Family Home (custom, 2500 SF) (GSF) | $150 | $250 | $450 |
| Single Family Home (luxury) (GSF) | $300 | $500 | $900 |
| Single Family Home (production) (GSF) | $100 | $160 | $250 |
| Urgent Care / Walk-In Clinic (GSF) | $250 | $400 | $600 |
| Veterinary Clinic (GSF) | $225 | $375 | $575 |
| Service / Item | Low | Average | High |
|---|---|---|---|
| Casework & Cabinets (medical) (LF) | $350 | $650 | $1,200 |
| Casework & Cabinets (standard) (LF) | $200 | $400 | $750 |
| Millwork (general) (GSF) | $0.5 | $2 | $6 |
| Millwork (healthcare/high-end) (GSF) | $3 | $8 | $18 |
| Rough Carpentry (GSF) | $1 | $3 | $7 |
| Wood Framing (light commercial) (SF floor) | $6 | $12 | $22 |
Upload it for instant AI analysis. We'll compare every line item against these benchmarks.
Analyze Your Quote Free →